• TSL to exit Somerset battery plant project

    TSL to exit Somerset battery plant project
    Distribution and data centre construction specialist TSL is understood to be stepping down as main works contractor on the Somerset mega battery plant project.
    The decision comes just six months after client Agratas, a subsidiary of industrial giant Tata, drafted in TSL to replace Sir Robert McAlpine on the vast gigafactory construction project.
    In a fresh twist on the delivery plan, M&E specialist NG Bailey is now being lined up to finish the plant, taking on the main building services fit-
  • Glazing specialist Bennett files administration notice

    Glazing specialist Bennett files administration notice
    One of the UK’s longest-established architectural glazing specialists has filed a notice of intention to appoint administrators.
    Bennett Architectural Aluminium Solutions, which has worked for major contractors including Laing O’Rourke, Balfour Beatty, Kier and Sir Robert McAlpine, filed the notice at the Manchester court on Friday 20 November.
    The move puts the future of the 66-year-old Staffordshire business and its 50-strong workforce in doubt.The filing gives the company breathing space
  • Crest Nicholson loss warning deepens to £40m as sales slump

    Crest Nicholson loss warning deepens to £40m as sales slump
    Crest Nicholson has warned annual operating losses could hit £40m as worsening house sales, rising build costs and fresh problems on a legacy flats scheme hammer profitability.
    The struggling house builder now expects an adjusted operating loss of £30m to £40m for the year to October after trading deteriorated sharply in the final months.
    Adding to its problems, the group is facing a further £15m to £20m provision on a non-standard apartment development completed around 10 years ago.The pro
  • £14bn frameworks to follow Burnham devolution drive

    Two new frameworks worth a combined £14m are being built around sub-regional lots to fit in with the government’s devolution drive.
    Procure Partnerships Framework is launching the tender process for the renewal of its National Construction Framework and a dedicated Civil Engineering & Infrastructure Framework.
    The four-year deals will be worth an estimated £8bn and £6bn respectively and are set to go live in October 2027.Lower-value lots will be awarded at a sub-regional level, allowing
  • Advertisement

  • Select lodges plans for £136m Manchester tower

    Select lodges plans for £136m Manchester tower
    Developer Select Property has submitted plans for a 31-storey residential tower in the St John’s district of Manchester.
    The proposed One St John’s scheme is expected to cost £136m to build and will deliver 381 flats in a 95m-high building overlooking the River Irwell on the western edge of the city centre.
    Designed by architect SimpsonHaugh, the tower will rise on the site of the vacant Albert Shed at the junction of New Quay Street and Water Street, next to the Marriott hotel.The project